Standard Costing – CA Final SCMPE Question Bank

Standard Costing – CA Final SCMPE Question Bank is designed strictly as per the latest syllabus and exam pattern.

Standard Costing – CA Final SCMPE Question Bank

Question 1.
Comment on efficiency and responsibility of the Sales Manager for not using scarce resources. (May 2018, 8 marks)
Answer:
(II) Comment on Efficiency and Responsibility of the Sales Manager
In general, Gross Profit (or contribution margin) is the joint responsibility of sales managers as well as of production managers. On one hand the sales manager is responsible for the sales revenue part, on the other hand the production manager is accountable for the cost – of-goods-sold component.

However, it is the top management who needs to ensure that the target profit is achieved by the organization. The sales manager is accountable for prices, volume, and mix of the product, whereas the production manager must control the costs of materials, labour, factory overheads and quantities of production. The purchase manager must purchase materials at budgeted prices. The personnel manager must employ right people at the right place with appropriate wage rates.

The internal audit manager must ensure that the budgetary figures for sales and costs are being adhered by all departments which are directly or indirectly involved in contribution of making profit. Thus, sales manager is not responsible for contribution lost due to excess usage or inefficient usage of resources in case of scarce resources. Hence, such contribution lost must be excluded from the sales contribution volume variance.

Standard Costing – CA Final SCMPE Question Bank

Question 2.
The following profit reconciliation statement has been prepared by the Cost Accountant of RSQ Ltd. for March, 2008 : (Nov 2008, 11 marks)
Standard Costing – CA Final SCMPE Question Bank 1
Budgeted production and sales volumes for March, 2008 were equal and the level of finished goods stock was unchanged, but the stock of raw materials decreased by 6,400 kg (valued at standard price) during the month.
The standard cost card is as under :
Standard Costing – CA Final SCMPE Question Bank 2
The actual labour rate was ₹ 2.24 lower than the standard hourly rate.

You are required to calculate :
(i) Actual quantity of material purchased
(ii) Actual production and sales volume
(iii) Actual number of hours worked
(iv) Actual variable and fixed overhead cost incurred.
Answer:
(i) Budgeted volume = \(\frac{\text { Budgeted profit }}{\text { Budgeted profit per unit }}\)
= \(\frac{2,40,000}{24.00}\)
= 10,000 units
Difference between actual and budgeted volume
= \(\frac{\text { Fixedoverheadvolume variance }}{\text { Standardfixedoverheadrate }}=\frac{1,96,000}{112}\) = 1,750 units
Actual Production = Budgeted volume – Difference between actual and budget volume
= 10,000 – 1,750
= 8,250 units

Standard Costing – CA Final SCMPE Question Bank

(ii) Actual production = 8,250 units
Material quantity = 4 kg. × 8,250
Less: Difference in material use
Material =\(\frac{\text { Usage variance }}{\text { Standard price }}\) = \(\frac{\text { Usage variance }}{\text { Standard price }}=\) = 1,600 kg.
Actual usages = 31,400 kg.
Less: Decrease in stock = 6,400 kg.
Actual purchases = 25,000 kg.

(iii) Actual hours 8,250 units × 4 hours = 33,000 hours
Difference in actual and standard
\(\frac{\text { Efficiency variance }}{\text { Standard rate }}=\frac{32,000(A)}{32.00}\) = 1,000 (A) hours
Actual hours = 34.00 hours

(iv) Actual variable overhead incurred:
Standard cost of variable overhead = 8,250 × 48 = ₹ 3,96,000
Total variable overhead cost variance
= [8,000(F)+12.000(A)] = ₹ 4,000 (A)
Actual variable overhead = ₹ 4,00,000

Standard Costing – CA Final SCMPE Question Bank

(v) Actual fixed overhead:
Budgeted fixed overhead =
Budgeted units × Budgeted rate
= 10,000 × 112 = ₹ 11,20,000
Expenditure variance = ₹ 4,000 (F)
Actual fixed overhead = ₹ 11,16,000
It can also be calculated as below:
Actual fixed overhead:
Standard fixed overhead .
= (Actual output × Standard fixed overhead
rate per unit) 8,250 × 112 = ₹ 9,24,000
Total fixed overhead variance
[1,96,000 (A) + 4,000 (F)] = ₹ 1.92.000 (A)
Actual fixed overhead = ₹ 11.16.000

(vi) Actual sales volume:
Sales volume profit variance = Standard profit per unit (Actual quantity of sales- Standard quantity of sales)
42,000 (A) = 24 (Actual quantity of Sales -10,000)
Actual quantity of sales = 8,250 units

Standard Costing – CA Final SCMPE Question Bank

Question 3.
The following information relates to labour of X Ltd. (Nov 2009, 10 marks)
Standard Costing – CA Final SCMPE Question Bank 3
In a 40 hour week, the gang produced 270 standard hours.
The actual number of semi-skilled workers is two times the actual number of unskilled workers. The rate variance of semi-skilled workers is ₹ 160 (F).

Find the following:
(i) The number of workers in each category
(ii) Total gang variance
(iii) Total Sub-efficiency variance
(iv) Total labour rate variance
(v) Total labour cost variance
Answer:
Standard Costing – CA Final SCMPE Question Bank 4
Working Note:
Standard hours produced = 270
Standard Mix : 270 ÷ 9 = 30
Standard Costing – CA Final SCMPE Question Bank 5
‘(Standard Rate – Actual Rate) Actual hrs.] = Rate Variance
Semi-skilled = 160
(3 – 2) Actual hrs = 160
Actual hrs = 160 (for semi – skilled)
Actual Semi-skilled = 2 (Unskilled actual)
160 = 2 (Unskilled)
Unskilled hrs (actual) = \(\frac{160}{2}\) = 80
Total Actual = 360
∴ Actual hrs – skilled = 360 – (160 + 80)
= 360 – 240 = 120

Category Skilled Semi-skilled Unskilled Total
Actual Hrs. 120 160 80 360
40 hr week \(\frac{120}{40}\) = 3 \(\frac{160}{40}\) = 4 \(\frac{80}{40}\) = 2
No. of Workers 3 4 2 9

Standard Costing – CA Final SCMPE Question Bank

(ii) Gang Variance :
= (Actual Hrs in Standard Ratio-Actual Hrs in Actual Ratio) × Standard Rate
= 1400 – 1280 = 120(F)

(iii) Sub-efficiency Variance:
= Standard Rate (Standard Hrs – Actual Hrs in Standard Ratio)
= 1050 – 1400 = 350 (A)

(iv) Total Labour Rate Variance:
= Actual Hrs (Standard Rate – Actual Rate)
= 1280 – 320 = 40 (A)

(v) Labour Cost Variance:
= (Standard Ratex Standard Hrs -Actual Rate × Actual Hrs.)
= 1050 – 1320 = 270 (A)

Standard Costing – CA Final SCMPE Question Bank

Question 4.
X Ltd. produces and sells a single product. Standard cost card per unit of the product is as follows: (May 2010, 12 marks)
Standard Costing – CA Final SCMPE Question Bank 6
A fixed production overhead has been absorbed on the expected annual output of 25,200 units produced evenly throughout the year. During the month of December, 2009, the following were the actual results for an actual production of 2,000 units:
Standard Costing – CA Final SCMPE Question Bank 7
The material price variance Is extracted at the time of receipt of materials. Material purchase were A 20,000 kg. @ ₹ 5.25 per kg; B 11,500 kg @ ₹ 5.70 per kg.

Required:
(i) Calculate all variances.
(ii) Prepare an operating statement showing Standard gross profit, Variances and Actual gross profit.
(iii) Explain the reason for the difference in actual gross profit given in the question and calculated in (ii) above.
Answer:
(i) Direct Material Variance
Material Price Variance = Standard Cost of Actual Quality – Actual Cost
(At the time of receipt) = PQ × SP – PO × AP
Or
= PQ × (SP – AP)
(A) = 20,000 kg. × ( 5.00 – ₹ 5.25)
= ₹ 5,000 (A)
(B) = 11,500kg. × (₹ 600 – ₹ 5.70)
= ₹ 3,450(F)
Total = ₹ 5,000 (A) + ₹ 3,450 (F)
= ₹ 1,550 (A)

Standard Costing – CA Final SCMPE Question Bank

Material Usage Variance = Standard Cost of Standard Quantity for Actual Output – Standard Cost of Actual Quantity
=SQ × SP – AQ × SP
Or
= SP × (SQ – AQ)
(A) = ₹ 5 × (5,000 units × 10 Kg. – 18,900 Kg.)
= ₹ 5,500 (F)
(B) = ₹ 6 × (2,000 units × 5 Kg. – 10,750 Kg.)
= ₹ 4,500(A)
Total = ₹ 5,500 (F) + ₹ 4,500 (A)
= ₹ 1,000(F)
Material Mlx Variance = Total Actual Quantity (units) × (Average Standard Price per unit of Standard Mix – Average Standard Price per unit of Actual Mix)
= 29,650 Kg. × \(\left(\frac{(₹ 50+₹ 30) \times 2,000 \text { units }}{2,000 \text { units } \times(10 \mathrm{Kg} .+5 \mathrm{Kg})}-\frac{₹ 5 \times 18,900 \mathrm{Kg}+₹ 6 \times 10,750 \mathrm{Kg} .}{18,900 \mathrm{Kg} .+10,750 \mathrm{Kg} .}\right)\)
= ₹ 866.66 ………… (A)
Material Yield Variance = Average Standard Price per unit of Standard Mix × [Total Standard Quantity (units) – Total Actual Quantity (units)]
= \(\left\{\frac{(₹ 50+₹ 30) \times 2,000 \text { units }}{2,000 \text { units } \times(10 \mathrm{Kg} .+5 \mathrm{Kg})}\right\}\) × [(10Kg. + 5Kg.)x 2,000 units – (18,900 Kg. + 10,750 kg.)]
= ₹ 1866.66 …………. (F)

Direct Labour Variances
Labour Rate Variance = Standard Cost of Actual Time – Actual Cost
= SR × AW* – AR × AH*
Or
= (SR – AR) × AH*
= (₹ 5 – \(\frac{₹ 50,400}{10,500 \text { hours }}\)) × 10,500 hours
= 2,100 (F)
AH* refers to Actual Hours Paid

Labour Efficiency Variance = Standard Cost of Standard Time for Actual Production – Standard Cost of Actual Time
= (SH × SR) – (AH × SR)
Or
(SH – AH) × SR
= ₹ 5.00 × (2,000 units × 5 hours – 10,300 hours)
= ₹ 1,500 (A)

Standard Costing – CA Final SCMPE Question Bank

Idle Time Variance = Standard Rate per Hour × Actual Idle Hours
= (AH* – SR) × (AH* × SR)
Or
= (AH* × AH*) × SR
= ₹ 5.00 × (10,500 hours – 10,300hours)
= ₹ 1,000 (A)
AH* refers to Actual Hours Worked

Variable Overhead Variances Cost Variance = Standard Variable Overheads for Production – Actual Variable Overheads
= 2,000 units × ₹ 601,15,000 = ₹ 5.000(F)
Expenditure Variance = Budgeted Variable Overheads for Actual Hours – Actual Variable Overheads
= 10,300 hours × ₹ 12 – ₹ 1,15,000
= ₹ 8,600 (F)
Efficiency Variance = Standard Variable Overheads for Production – Budgeted Variable Overheads for Actual Hours
= 2,000 units × ₹ 60 – 10,300 hours × ₹ 12
= ₹ 3,600 (A)

Fixed Overhead Variances Cost Variance = Absorbed Fixed Overheads – Actual Fixed Overheads
= 2,000 units × ₹ 25.00 – ₹ 56,600
= ₹ 50,000 – ₹ 56,600
= ₹ 6,600 (A)
Expenditure Variance = Budgeted Fixed Overheads – Actual Fixed Overheads
= 2,100 units × ₹ 25.00 – ₹ 56,600
= ₹ 52,500 – ₹ 56,600
= ₹ 4,100 (A) .
Volume Variance = Absorbed Fixed Overheads – Budgeted Fixed Overheads
= ₹ 50,000 – ₹ 52,500
= ₹ 2,500 (A)

Standard Costing – CA Final SCMPE Question Bank

(ii) Reconciliation Statement
Standard Costing – CA Final SCMPE Question Bank 8

(iii) Actual gross profit given in the question is ₹ 67,500 while calculated operating profit in statement is ₹ 67,450. The difference amount is due to material price variance that is calculated at the time of receipt of material instead of consumption of material price variance that is calculated at time of receipt of material instead of consumption of material.
Standard Costing – CA Final SCMPE Question Bank 9

Question 5.
2010- Nov (3] (a)
A company is engaged in manufacturing of several products. The following data have been obtained from the record of a machine shop for an average month: (Nov 2010, 10 marks)
Standard Costing – CA Final SCMPE Question Bank 10
There was a special holiday in August 2010.

Required:
(i) Calculate efficiency, activity, calendar and standard capacity usages ratio.
(ii) Calculate all the relevant fixed overhead variances.
(iii) Calculate variable overheads expenditure and efficiency variance.
Answer:
Standard Costing – CA Final SCMPE Question Bank 11
Standard Costing – CA Final SCMPE Question Bank 12

Budgeted Fixed Overheads

Standard Rate × Standard Hours (1) Standard Rate × Actual Hours (2) Standard Rate × Revised Budgeted Hours (3) Standard Rate × Budgeted Hours (4) Actual overheads (5)
2.91 × 22550 = 65621 2.91 × 20500 = 59655 2.91 × 24840 = 72284 Given = 75400 Given = 78800

Fixed Overhead Efficiency Variance (1) – (2) ₹ 5,966(F)
Fixed Overhead Capacity Variance (2) – (3) ₹ 12,629 (A)
Fixed Overhead Calendar Variance (3) – (4) ₹ 3,116(A)
Fixed Overhead Volume Variance (1) – (4) ₹ 9,779 (A)
Fixed Overhead Expenditure Variance (4) – (5) ₹ 3,400 (A)
Fixed Overhead Variance (1) – (5) ₹ 13,179 (A)

Standard Costing – CA Final SCMPE Question Bank

Question 6.
A company actually sold 8000 units of A and 10,000 units of B at ₹ 12 and ₹ 16 per unit respectively against a budgeted sale of 6000 units of A at ₹ 14 per unit and 9000 units of B at ₹ 13 per unit. The standard costs of A and B are ₹ 8 and ₹ 10 per unit respectively and the corresponding actual costs are ₹ 5.5 and 114.5 per unit.

Compute the product wise sales margin mix and sales margin price variances, indicating clearly, whether the variances are favourable or adverse. (May 2011, 5 marks)
Answer:
Standard Costing – CA Final SCMPE Question Bank 13
Sales Margin Mix Varlance
(Actual Qty in Actual Mix – Actual Qty in Budgeted Mix) × Budgeted Margin
A: (8,000 – 7,200) × 6 = 4,800 (Fav)
B: (10,000 – 10,800) × 3 = – 2,400 (Adv)
Total Mix Variance = 2,400 (Fav)
Sales Margin Price Variance = Actual Qty (Actual Margin – Budgeted Margin)
A 8,000(4 – 6) = -16,000 (A).
B 10,000(6 – 3) = 30.000 (F)
= 14.000 (F)

Standard Costing – CA Final SCMPE Question Bank

Question 7.
The budget and actual operating data for 2010-11 pertaining to 4 products in a store area given below:

Budgeted date for 2010-11 Actual operating results in 2010-11
Product Gallons Selling price (₹ per gallon) Variable costs (₹ per gallon) Gallons Selling price (₹ per gallon) Variable costs (₹ per gallon)
V 2,50,000 1.2 0.5 1,80,000 1.00 0.45
C 3,00,000 1.5 0.6 2,70,000 1.35 0.50
S 2,00,000 1.8 0.7 3,30,000 2.00 0.75
A 50,000 2.5 1.00 1,80,000 3.00 1.20

You are required to compute for the individual products and in total: (Nov 2011, 10 marks)
(i) the sales margin price variance
(ii) the sales margin mix variance and
(iii) the sales margin volume variance
Indicate whether the variances are favourable (F) or unfavourable (A or U).
Answer:
Working Notes:
Standard Costing – CA Final SCMPE Question Bank 14
Standard Costing – CA Final SCMPE Question Bank 15

Standard Costing – CA Final SCMPE Question Bank

Question 8.
The standard set for a chemical mixture of company is as under: (May 2012)

Material Standard Mix (%) Standard Price ₹/kg.
A 80 50
B 20 100

Standard yield in production is 75%.
The actual quantity produced was 1800 kg. of output from the following:

Material Quantity (kg.) Actual price
A 1400 60
B 600 90

Calculate the total material price, mix and yield variances, indicating whether they are favourable (F) or adverse (A or U). (6 marks)
Answer:
Standard Costing – CA Final SCMPE Question Bank 16
SP – Standard Price per Kg, SQ : Standard Quantity for actual production
RSQ – Revised Standard Quantity, AQ – Actual Quantity used, AP – Actual Price per kg.

Standard Costing – CA Final SCMPE Question Bank

Variances: (Figures ₹)

Variances Material Yield Variance (I – II) Material Mix. Variance (II – III) Material Price Variance (III – IV)
A 16,000 F 10,000 F 14,000 A
B 8,000 F 20,000 A 6,000 F
TOTAL 24,000 F 10,000 A 8,000 A

Note: Standard Input = 1800 / 0.75 = 2,400 kgs. Hence Standard quantity of A is 2,400 × 0.8 = 1920 kgs. and B = 2400 × 0.2 = 480 kgs.

Standard Costing – CA Final SCMPE Question Bank

Question 9.
Sunglow Limited manufacturers and sells a single product. From the records of the company the following information is available for November 2012: (Nov 2012, 9 marks)
The standard cost comprises the following :
Standard Costing – CA Final SCMPE Question Bank 17
The budgeted selling price is ₹ 700 each and the budgeted sales for the month were 14,000 units.
The following were the transactions for the month:
Standard Costing – CA Final SCMPE Question Bank 18
Sales: 9,000 units at ₹ 700 each and 3,500 units at ₹ 750 each Required:
Calculate
(i) Material price variance;
(ii) Material mix variance;
(iii) Labour rate variance
(iv) Labour efficiency variance
(v) Variable overhead efficiency variance; and
(vi) Fixed overhead efficiency variance.
Answer:
Statement showing ‘Standard Cost of Material’ and ‘Actual Cost of Material’-Production 11,000 units
Standard Costing – CA Final SCMPE Question Bank 19
*Actual Quantity in Standard Proportion.
Statement showing ‘Standard Cost of Wages’ and ‘Actual Cost of Wages’- Production 11,000 units

Standard Cost Actual Cost
Hours Rate ₹ Amount Hours Rate ₹ Amount ₹
4,40,000 hrs. [11,000 × (1,600/40) 40 1,76,00,000 3,98,000 hrs. 22.613 (Appx.) 90,00,00

Standard Costing – CA Final SCMPE Question Bank

(i) Material Price Variance = Actual Quantity × Std. Price – Actual Cost
Material ‘X’ = 82,400 Units × ₹ 40 – ₹ 33,84,000
= ₹ 88,000(A)
Material ‘Y’ = 2,46,400 Units × ₹ 70 – ₹ 1,73,88,000
= ₹ 1,40,000(A)
Material ‘Z’ = 1,64,000 Units × ₹ 25 – ₹ 40,40,000
= ₹ 60,000 (F)
Total = ₹ 88,000 (A) + ₹ 1,40,000(A) + ₹ 60,000 (F)
= ₹ 1,68,000(A)

(ii) Material Mix Variance = Std. Price × (Revised Actual Quantity – Actual Quantity)
Material ‘X’ = ₹ 40 × (82,133 units – 82,400 units)
= ₹ 10.680(A)
Material ‘Y’ = ₹ 70 × (2,46,400 units – 2,46,400 units)
= ₹ 0
Material ‘Z’ = 7 25 × (1,64,267 units -1,64,000 units)
= 6,675 (F)
Total = ₹ 10,680 (A) + ₹ 0 + ₹ 6,675 (F)
= ₹ 4,005 (A)

(iii) Labour Rate Variance = Actual hours × (Std. Rate – Actual Rate)
= 3,98,000 hrs. × (₹ 40 – ₹ 22.613)
= ₹ 69,20,000 (F)

(iv) Labour Efficiency = Std. Rate × (Standard hours – Actual hours)
Variance = ₹ 40 × (4,40,000 hrs. – 3,98,000 hrs.)
= ₹ 16,80,000 (F)

(v) Variable Overhead Efficiency Variance
= Std. Rate per Hour × (Standard Hours for Actual Production – Actual Hours)
= (₹ 400/40 hrs.) × [(11,000 units × 40 hrs.) – (3,98,000 hrs.)]
= ₹ 4,20,000 (F)

(vi) Fixed Overhead Efficiency Variance
= Std. Rate per Hour × (Standard Hours for Actual Production – Actual Hours)
= (₹ 600/40 hrs.) × [(11,000 units × 40 hrs.) – (3,98,000 hrs.)]
= ₹ 6,30,000 (F)
Assumption: It is assumed that Opening Inventory is valued at Standard Cost.

Standard Costing – CA Final SCMPE Question Bank

Question 10.
The following are the information regarding overheads of a company: (May 2013, 8 marks)
(a) Overheads cost variance = ₹ 2,800 (A)
(b) Overheads volume variance = ₹ 2,000 (A)
(c) Budgeted overheads = ₹ 12,000
(d) Actual overhead recovery rate = ₹ 8 per hour
(e) Budgeted hours for the period = 2400 hours

You are required to compute the following:
(i) Overheads expenditure variance.
(ii) Actual incurred overheads.
(iii) Actual hours for actual production.
(iv) Overheads capacity variance.
(v) Overheads efficiency variance.
(vi) Standard hours for actual production.
Answer:
Overheads Cost Variance = ₹ 2,800 (A)
Overheads Volume Variance = ₹ 2,000 (A)
Budgeted Overheads = ₹ 12,000
Actual Overhead Recovery Rate = ₹ 8 per hour
Budgeted Hours for the period = 2,400 hours

(i) Overheads Expenditure Variance = Overheads Cost Variance (-) Overheads Volume Variance
= ₹ 2,800 (A) – ₹ 2,000 (A)
= ₹ 800 (A)

(ii) Overheads Expenditure Variance = Budgeted Overheads (-) Actual Overheads
⇒ ₹ 800 (A) = ₹ 12,000 (-) Actual Overheads
Therefore, Actual Overheads = ₹ 12,800

Standard Costing – CA Final SCMPE Question Bank

(iii) Actual hours for actual production
= \(\frac{\text { Actual Overheads }}{\text { Actual OverheadRecovery Rate Per Hour }}\)
= \(=\frac{\text { Actual Overheads }}{\text { Actual OverheadRecovery Rate Per Hour }}\)
= 1,600 hours

(iv) Overheads Capacity Variance = Budgeted Overheads for Actual Hours (-) Budgeted Overheads
= ₹ 5* × 1600 hrs. – ₹ 12,000
= ₹ 8,000 – ₹ 12,000
= ₹ 4,000 (A)
[Note : Refer working note]

(v) Overheads Efficiency Variance = Absorbed Overheads (-) Budgeted Overheads for Actual Hour
= ₹ 10,000 – ₹ 5* × 1600 hours
= ₹ 2.000(F)
[Note : Refer working note]

(vi) Standard hours for actual production = \(\frac{\text { AbsorbedOverheads }}{\text { Standard OverheadRatePerHour }}\)
= \(=\frac{₹ 10,000}{₹ 5}\) = 2,000
[Note : Refer working note]

Working Notes:
Overhead Cost Variance = Absorbed Overheads (-) Actual Overheads
⇒ ₹ 2,800 (A) = Absorbed Overheads (-) ₹ 12,800
Therefore, Absorbed Overheads = ₹ 10,000
Standard Rate per hour = \(\frac{\text { BudgetedOverheads }}{\text { Budgeted Hours }}\) = \(\frac{₹ 12,000}{2,400 \text { hours }}\)

Standard Costing – CA Final SCMPE Question Bank

Question 11.
In a 40 hour week, the gang produced 270 standard hours. The actual number of semi-skilled workers is two times the actual number of unskilled workers. The rate variance of semi-skilled workers is ₹ 160 (F).

Find the following:
(i) The number of workers in each category
(ii) Total gang variance
(iii) Total sub-efficiency variance
(iv) Total labour rate variance
Indicate if the variances are Favourable (F) or Adverse (A or U). (8 marks)
Answer:
Woking Note
Computation of Standard Hours Category Wise
Standard Costing – CA Final SCMPE Question Bank 20
Computation of Actual Hours Category Wise
Semi-Skilied Workers
Labour Rate Variance = Standard Cost of Actual Time – Actual Cost
Or = Standard Rate × Actual Hours – Actual Rate × Actual Hours
Or = Actual Hours × (Standard Rate – Actual Rate)
⇒ ₹ 160(F) = Actual Hours × (₹ 3 – ₹ 2)
⇒ Actual Hours =160 Hours

(i) Computation of Total No. of Workers In Each Category
Standard Costing – CA Final SCMPE Question Bank 21
(*) Total No. of Actual Hours is 360 hrs. (40 hrs. × 9 workers)
(ii), (iii), & (iv)
Computation of Variances
Statement Showing Standard & Actual cost
Standard Costing – CA Final SCMPE Question Bank 22

Total Gang Variance
= Total Actual Time Worked (hours) × {Average Standard Rate per hour of Standard Gang
Less: Average Standard Rate per hour of Actual Gang@}
@on the basis of hours worked
= 360 hrs. × \(\left(\frac{₹ 1,050}{270 \mathrm{hrs} .}-\frac{₹ 6 \times 120 \mathrm{hrs} .+₹ 3 \times 160 \mathrm{hrs} .+₹ 1 \times 80 \mathrm{hrs} .}{360 \mathrm{hrs} .}\right)\)
= ₹ 120(F)

Total Sub-Efficiency Variance
= Average Standard Rate per hour of Standard Gang × {Total Standard Time (hours’) Less Total Actual Time Worked (hours)}
= \(\left(\frac{₹ 1,050}{270 \text { hrs }}\right)\) × (270 hrs. – 360 hrs.)
= ₹ 350 (A)

Labour Rate Variance
= Standard Cost of Actual Time – Actual Cost
Or = Standard Rate × Actual Hours – Actual Rate × Actual Hours
Or = Actual Hours × (Standard Rate – Actual Rate)
Skilled Workers = 120 hrs. × (₹ 6 – ₹ 7)
= ₹ 120 (A)
Semi-Skilled Workers = 160 hrs. × (₹ 3 – ₹ 2)
= ₹ 160(F)
Skilled Workers = 80 hrs. × (₹ 1 – ₹ 2)
= ₹ 80 (A)
Total = ₹ 120(A) + ₹ 160(F) + ₹ 80 (A)
= ₹ 40 (A)

Standard Costing – CA Final SCMPE Question Bank

Question 12.
Compute the missing data, indicated by question marks, from the following: (Nov 2014, 7 marls)
Standard Costing – CA Final SCMPE Question Bank 23
Material Mix variance for both product together was ₹ 90 adverse.
Answer:
Let SQ for product B = Q units
Material usage variance for B
= (SQ × SP) – (AQ × AP)
600 A = (SQ × 30) – (70 × 30)
600A = 30 SQ – 2100
30 SQ = 2100 – 600
SQ = \(\frac{1500}{30}\)
SQ = 50 units
So; std mix is 1 : 1
Let AQ of material A be K units. Total AQ = (K + 70) units. Since std. mix is 1 : 1 RAQ of A and B are each
\(\left(\frac{K+70}{2}\right)\) and \(\left(\frac{K+70}{2}\right)\) respectively.
It s given that material mix variance = (SQ × SP). (RAQ × SP)
90A = \(\left[\frac{(K+70)}{2} \times 24+\frac{(K+70)}{2} \times 30\right]\) – [(K × 124) + (70 × 30)]
90A = (12K + 840 + 15K + 1050) – (24K + 2100)
90A = (27K + 1890 – 24K – 2100)
120 = 3K
K = 40
Total AQ = 40 + 70 = 110 units
RAQ for A and B is 55 units each

Standard Costing – CA Final SCMPE Question Bank

Variance computation chart

Particulars (1) SQ × SP (2) RAQ × SP (3) AQ × SP (4) AQ × AP
A 50 × 24 = 1200 55 × 24 = 1320 40 × 24 = 960 40 × 30 = 1200
B 50 × 30 = 1500 55 × 30 = 1650 70 × 30 = 2100 70 × 40 = 2800
2700 2970 3060 4000

Material wise Break-up of variances

Particulars Prod. A Prod. B Total
(A) Yield variance [(1)-(2)] 120 A 150 A 270 A
(B) Mix variance [(2)-(3)] 360 F 450 A 90 A
(C) Usage variance [(1)-(3)] 240 F 600 A 360 A
(D) Price variance [(3)-(4)] 240 A 700 A 940 A
(E) Total material cost
Variance [(1)- (4)] 0 1300 A 1300 A

Alternative Solution:
Calculation of Missing Figures (Working)
Statement Showing Standard & Actual Cost (Incomplete)
Standard Costing – CA Final SCMPE Question Bank 24
Standard Input (Kg.) for Product ‘B’:
Let ‘T’ Kgs. be the Standard Quantity of Input for Product B
Material Usage Variance = (SQ × SP) – (AQ × SP)
Or
= (SQ – AQ) × SP

For Product B:
₹ 600 (A) = (T Kgs. – 70 Kgs.) × ₹ 30
⇒ -600 = 30T – 2,100
⇒ 30T = 1,500
⇒ T = 50 Kg.
Therefore, Standard Quantity of input for product B is 50 Kg.

Actual Input (Kg.) for Product ‘A’:
Let ‘N’ Kg. be the Actual Quantity of Input for Product A
Material Mix Variance = Std. Price × (Actual Quantity in Std. Proportion – Actual Quantity)
Or
Material Mix Variance (A + B) = Material Mix Variance (A) + Material Mix Variance (B)
Standard Costing – CA Final SCMPE Question Bank 25

Standard Costing – CA Final SCMPE Question Bank

Computation of Variances of Product A
Material Price Variance = Standard Cost of Actual Quantity – Actual Cost
= (SP × AQ) – (AP × AQ)
Or
= (SP – AP) × AQ
= (₹ 24.00 – ₹ 30.00) × 40 Kg.
= ₹ 240 (A)
Material Usage Variance = Standard Cost of Standard Quantity for Actual Production – Standard Cost of Actual Quantity
= (SQ × SP) – (AQ × SP)
Or
= (SQ – AQ) × SP
= ₹ 24.00 × (50 Kg. – 40 Kg.)
= ₹ 240 (F)
Total Material Cost Variance = Standard Cost – Actual Cost
= (SQ × SP) – (AQ × AP)
= ₹ 1,200 – ₹ 1,200
= ₹ 0
Computation of Variances of Product B
Material Price Variance = Standard Cost of Actual Quantity – Actual Cost
= (SP × AQ) – (AP × AQ)
Or
= (SP – AP) × AQ
= (₹ 30.00 – ₹ 40.00) × 70 Kg.
= ₹ 700 (A)
Standard Cost – Actual Cost
= (SQ× SP) – (AQ × AP)
= ₹ 1,500 – ₹ 2,800
= ₹ 1.300(A)

Important Note:
Calculation as well as Presentation may be different in this chapter. But there will be no change in final answer.

Standard Costing – CA Final SCMPE Question Bank

Question 13.
The standard cost of a certain chemical mixture is as under: (May 2015, 8 marks)
40% of Material A @ ₹ 30 per kg
60% of Material B @ ₹ 40 per kg
A standard loss of 10% of input is expected in production. The following actual cost data is given for the period.
350 kg Material – A at a cost of ₹ 25
400 kg Material – B at a cost of ₹ 45 Actual weight produced is 630 kg.

You are required to calculate the following variances raw material wise and indicate whether they are favourable (F) or adverse (A):
(i) Cost variance
(ii) Price variance
(iii) Mix variance
(iv) Yield variance
Answer:
Total Actual weight produced = 630 kg.
Add: Normal loss [\(\frac{630}{90 \%}\) × 10%] = 70 kg.
Actual Input = 700 kg.
Standard Costing – CA Final SCMPE Question Bank 26
(i) Material Cost Variance Std. cost – Actual cost
Product A = 8,400 – 8,750 = – 350 (A)
Product B = 16800 – 18,000 = -1.200(A)
= 1.550 (A)

(ii) Material Price Variance = (SR – AR) × AQ.
Product A = (30 – 25) × 350 = 1,750 (F)
Product B = (40 – 45) × 400 = -2.000 (A)
= -250(A)

(iii) Material Mix Variance = SP × (RAQ – AQ)
A = ₹ 30 × (300 Kg – 350 Kg)
= ₹ 1,500(A)
B = ₹ 40 × (450Kg. – 400Kg.)
= ₹ 2,000 (F)
Total = ₹ 1,500 (A) + ₹ 2,000 (F)
= ₹ 500(F)

(iv) Material Yield Variance = (Total Std. Qty. – Total Act. Qty.) × Avg. Std. price p.u. of Std. Mix.
= (700 – 750) × \(\frac{25,200}{700}\)
= -1800 (A)

Standard Costing – CA Final SCMPE Question Bank

Question 14.
Alpha Ltd. uses standard costing system for manufacturing its single product ‘APS’. (Nov 2015, 8 marks)
Standard cost card is as follows:
Standard Costing – CA Final SCMPE Question Bank 27
Actual and budgeted activity levels in units for the month of September are:
Standard Costing – CA Final SCMPE Question Bank 28
Actual sales revenue and variable costs for the month of September are given as under:
Standard Costing – CA Final SCMPE Question Bank 29

Calculate:
(i) Direct Labour Rate Variance
(ii) Direct Labour Efficiency Variance .
(iii) Sales Volume Variance .
(iv) Sales Price Variance
(v) Comment on your findings in (i) and (ii) above.
Answer:
(i) Direct labour rate variance = Standard cost for Actual Hours Actual Cost
= (SR × AH) – Actual Cost
= (8 × 3,00,000) – 24,42,000
= 24,00,000 – 24,42,000
= – 42.000(A)

(ii) Direct labour efficiency variance
= Standard cost of standard time for Actual production – Standard cost for Actual time
= (SH × SR) – (AH × SR)
= (52,000 × 6) × 8) – (3,00,000 × 8)
= 24,96,000 – 24,00,000
= 96,000 (F)

(iii) Sales volume variance = Standard sales – Budgeted sales
= BP × AQ – BP × BQ
= (AQ – BQ) × BP
= (51,200 – 50,000) × 120
= 1,44,000 (F)

Standard Costing – CA Final SCMPE Question Bank

(iv) Sales price variance = Actual Qty. × (AP – BP)
= 51,200 × \(\left(\frac{61,33,760}{51,200}-120\right)\)
= – 10,240 (A)

(v) Comment:
Direct Labour Rate Variance
Adverse Labour Rate Variance indicates that the labour rate per hour paid is more than the set standard. The reason may include among other things such as:

  1. While setting standard, the current/ future market conditions like pending labour negotiation/ cases, has not been considered (or predicted) correctly. ‘
  2. The labour may have been told that their wage rate will be raised or bonus will be paid if they work efficiently.

Direct Labour Efficiency Variance
It indicates that the workers have produced actual production quantity in less time than the time allowed. The reason for favourable labour efficiency variance may include among the other things as follows:

  1. While setting standard, workers efficiency could not be estimated properly, this may happen due to non-observance of time and motion study.
  2. The workers may be new in the factory, hence, efficiency could not be predicted properly.

Standard Costing – CA Final SCMPE Question Bank

Question 15.
A company operates a standard cost system to control the variable works cost of its only product. The following are the details of actual production, costs and variances for November, 2015. (May 2016, 8 marks)

Production and cost (actual)
Production – 10,000 units
Direct Materials (1,05,000 kg.) – ₹ 5,20,000
Direct Labour (19,500 hrs.) – ₹ 3,08,000
Variable Overheads – ₹ 4,10,000

Cost variances
Direct materials — Price : ₹ 5,000 (F)
Direct materials — Usages : ₹ 25,000 (A)
Direct labour — Rate : ₹ 15,500 (A)
Direct labour — Efficiency : ₹ 7,500 (F)
Variable overheads : ₹ 10.000(A)

The Cost Accountant finds that the original standard cost data for the product is missing from the cost department files. The variance analysis for December, 2015 is held up for want of this data.

You are required to calculate:
(i) Standard price per kg of direct material.
(ii) Standard quantity for each unit of output.
(iii) Standard rate of direct labour hour.
(iv) Standard time for actual production.
(v) Standard variable overhead rate.
Answer:
(i) Standard Price per Kg. of Direct Material:
Material Price Variance = Standard Cost of Actual Quantity – Actual Cost
– 5,000 (F) = Standard Cost of Actual Quantity – ₹ 5,20,000
Standard Cost of Actual Quantity
= ₹ 5,20,000 + ₹ 5,000
= ₹ 5,25,000
Standard Cost of Actual Quantity = Standard Price per Kg. × Actual Quantity
⇒ ₹ 5,25,000 = Standard Price per Kg. × 1,05,000 Kg.
Standard Price per Kg. = \(\left(\frac{₹ 5,25,000}{1,05,000 \mathrm{Kg} .}\right)\)
= ₹ 5

Standard Costing – CA Final SCMPE Question Bank

(ii) Standard Quantity for each unit of output:
Material Usage Variance = Standard Cost of Standard Quantity for Actual Output – Standard Cost of Actual Quantity
⇒ 25,000 (A) = Standard Cost of Standard Quantity for Actual Output – ₹ 5,25000
Standard Cost of Standard Quantity for Actual Output
= ₹ 5,25,000 – ₹ 25000
= ₹ 5,00,000
Standard Cost of Standard Time for Actual Production = Standard Rate per hr. × Standard Time for Actual Production
⇒ ₹ 3,00,000 = ₹ 15 × Standard Time for Actual Output
Standard Quantity for Actual Output = \(\left(\frac{₹ 5,00,000}{₹ 5}\right)\)
Standard Quantity for each unit of output = \(\left(\frac{1,00,000 \mathrm{Kg} .}{10,000 \text { units }}\right)\)
= 10Kg.

(iii) Standard Rate of Direct Labour Hour
Direct Labour Rate Variance = Standard Cost of Actual Time – Actual Cost
⇒ 15,500 (A) = Standard Cost of Actual Time – ₹ 3,08,000
Standard Cost of Actual Time = ₹ 3,08,000 – ₹ 15.500
= ₹ 2,92,500
Standard Cost of Actual Time = Standard Rate per hr. × Actual Hours
⇒ ₹ 2,92500 = Standard Rate per hr. × 19,500 hrs.
Standard Rate per hr. = \(\left(\frac{₹ 2,92,500}{19,500 \mathrm{hrs} .}\right)\) = ₹ 15

(iv) Standard Time for Actual Production
Labour Efficiency Variance = Standard Cost of Standard Time for Actual Production – Standard Cost of Actual Time
⇒ 7,500 (F) = Standard Cost of Standard Time for Actual Production – ₹ 2,92,500
Standard Cost of Standard Time for Actual Production
= ₹ 2,92,500 + ₹ 7,500
= ₹ 3,00,000
Standard Cost of Standard Time for Actual Production
= Standard Rate per hr. × Standard Time for Actual Production
⇒ ₹ 300,000 = ₹ 15 × Standard Time for Actual Production
Standard Time for Actual Production
= \(\left(\frac{₹ 3,00,000}{₹ 15}\right)\)
= 20,000 hrs.

Standard Costing – CA Final SCMPE Question Bank

(v) Standard Variable Overhead Rate
Variable Overhead Variance = Standard Variable Overheads for Production – Actual Variable Overheads
⇒ 10.000(A) = Standard Variable Overheads for Production – ₹ 4,10,000
Standard Variable Overheads for Production
= ₹ 4,10,000 – ₹ 10,000
= ₹ 4,00,000
Standard Variable Overheads for Production
= Standard Variable Overhead Rate per Unit × Actual Production (Units)
⇒ ₹ 4,00,000 = Standard Variable Overhead Rate per Unit × 10,000 units
Standard Variable Overhead Rate per unit
= \(\left(\frac{₹ 4,00,000}{10,000 \text { units }}\right)\)
= ₹ 40
Or
Standard Variable Overheads for Production
= Standard Variable Overhead Rate per Hour × Standard Hours for Actual Production
⇒ ₹ 4,00,000 = Standard Variable Overhead Rate per Hour × 20,000 hrs.
Standard Variable Overhead Rate per hour
= \(\left(\frac{₹ 4,00,000}{20,000 \mathrm{hrs}}\right)\)
= ₹ 20

Standard Costing – CA Final SCMPE Question Bank

Question 16.
Zed company manufacturers two types of flooring rolls. Budgeted and actual data for 2015 are : (Nov 2016, 8 marks)
Standard Costing – CA Final SCMPE Question Bank 30
Compute:
(i) Sales Mix Variance and Sales Quantity Variance by type of flooring rolls and in total.
(ii) Market Share Variance and Market Size Variance.
Answer:
(a) Workings
Statement Showing “Budgeted Vs Actual Figures”
Standard Costing – CA Final SCMPE Question Bank 31
Budgeted Market Share (in %) = \(\frac{8,00,000 \text { Rolls }}{80,00,000 \text { Rolls }}\)
= 10%
Actual Market Share (in %) = \(\frac{8,40,000 \text { Rolls }}{70,00,000 \text { Rolls }}\)
= 12%
Average Budgeted Margin (per Roll) = \(\frac{₹ 340 \text { Lacs }}{8,00,000 \text { Rolls }}\)
= ₹ 42.50

Standard Costing – CA Final SCMPE Question Bank

Computation of Variances Sales Mix Variance = Standard Margin Less Revised Standard Margin
Or
= (AQ × BM) – (RAQ × BM)
Or
= BM × (AQ – RAQ)
Domestic = ₹ 40 × (5,88,000 – 630,000)
= ₹ 16,80,000 (A)
Industrial = ₹ 50 × (2,52,000 – 2,10,000)
= ₹ 21,00,000 (F)
Total = ₹ 16,80,000 (A) + ₹ 21,00,000 (F)
= ₹ 4,20,000 (F)

Sales Quantity Variance = Revised Standard Margin Less Budgeted Margin
Or
= (RAQ × BM) – (BQ × BM)
Or
= BM × (RAQ – BQ)
Domestic = ₹ 40 × (6,30,000 – 6,00,000)
= ₹ 12,00,000 (F)
Industrial = ₹ 50 × (2,10,000 – 2,00,000)
= ₹ 5,00,000 (F)
Total = ₹ 12,00,000 (F) + ₹ 5,00,000 (F)
= ₹ 17,00,000 (F)
Market Size Variance = Budgeted Market Share %. × (Actual Industry Sales Quantity in units – Budgeted Industry Sales Quantity in units) × (Average Budgeted Margin per unit)
= 10% × (70,00,000 Rolls – 80,00,000 Rolls) × ₹ 42.50
= ₹ 42,50,000 (A)

Market Share Variance = (Actual Market Share % – Budgeted Market Share %) × (Actual Industry Sales Quantity in units) × (Average Budgeted Margin per unit)
= (12% – 10%) × 70,00,000 Rolls × ₹ 42.50
= ₹ 59,50,000 (F)

Standard Costing – CA Final SCMPE Question Bank

Question 17.
The following data pertains to a company which uses standard marginal costing for manufacture and sale of a single product during the year. (May 2017, 8 marks)

Particulars Budget Actual
Sales (in units) 60,000 66,000
Sales (₹) 1,80,00,000 2,14,50,000
Direct Materials (₹) 28,80,000 36,30,000
Direct Labour (₹) 43,20,000 52,80,000
Variable Overheads (₹) 72,00,000 81,84,000
Total Variable Costs 1,44,00,000 1,70,94,000

Additional information is as follows:

Standard Actual
Direct material price per kg ₹ 12 ₹ 11
Direct labour rate per hour ₹ 9 ₹ 10

Calculate the following variance for the year and indicate the type of variance favourable (F), unfavourable (U) or adverse (A).
(i) Direct material usage variance
(ii) Direct material price variance
(iii) Direct labour efficiency variance
(iv) Direct labour rate variance
(v) Variable overhead cost variance
(vi) Sales margin volume variance
Answer:
(i) Direct Material Usage Variance:
Direct Material Usage Variance
= (Standard Quantity – Actual Quantity) × Standard Rate
= (2,64,000 – 3,30,000) × 12
Direct Material Usage Variance = 7,92,000 (A)

Standard Costing – CA Final SCMPE Question Bank

(ii) Direct Material Price Variance:
Direct Material Price Variance
= (Standard Price – Actual Price) × Actual Quantity
= (12 – 11) × 3,30,000
Direct Material Price Variance = 3,30,000 (F)

(iii) Direct Labour Efficiency Variance:
Direct Labour Efficiency Variance
= (Standard hours – Actual hours) × Standard Rate
= (5,28,000 – 5,28,000) × 9
Direct Labour Efficiency Variance = NIL

(iv) Direct Labour Rate Variance:
Direct Labour Rate Variance
= (Standard Rate – Actual Rate) × Actual hours
= (9 – 10) × 5,28,000
Direct Labour Rate Variance = 5,28,000 (A)

(v) Variable Overhead Cost Variance:
Variable Overhead Cost Variance
= (Standard input for actual output – Actual input for actual output)
= (79,20,000 – 81,84,000)
Variable Overhead Cost Variance = 2,64,000 (A)

(vi) Sales Margin Volume Variance:
= Standard Margin – Budgeted Margin*
= \(\left(\frac{₹ 36,00,000}{60,000 \text { units }} \times 66,000 \text { units }\right)\) – ₹ 36,00,000
= ₹ 3,60,000 (F)
(*) Budgeted Margin
= ₹ 1,80,00,000 – ₹ 1,44,00,000 = ₹ 36,00,000

Standard Costing – CA Final SCMPE Question Bank

Working Note:
1. Calculation for Material (Standard input for Actual Output)

Standard Actual
Material Kg. Rate Amount Kg. Rate Amount
2,64,000 12 31,68,000 3,30,000 11 36,30,000

2. Calculation for Labour (Standard hours for Actual output)

Standard Actual
Labour Hours Rate Amount Hours Rate Amount
5,28,000 9 47,52,000 5,28,000 10 52,80,000

3. Calculation for variable Overhead Cost:
Standard input for actual output = \(\frac{72,00,000}{60,000}\) × 66,000
= 79,20,000

4. Calculation for Sales Margin:
(i) Calculation fro Profit on Sales
Standard Costing – CA Final SCMPE Question Bank 32
(ii) Sales Margin

Standard Actual
Sales Margin Unit Rate Amount Unit Rate Amount
60,000 159 95,40,000 66,000 180 1,18,80,000

Standard Costing – CA Final SCMPE Question Bank

Question 18.
S. Ltd. produces and sells a single product. The product is manufactured by mixing two raw materials Q and R. The standard cost date of the product is as follows: (Nov 2017, 8 marks)
Standard Costing – CA Final SCMPE Question Bank 33
The fixed production overhead absorption rate is based on the budgeted production.

Calculate Sales price variance, Sales volume variance, Material price variance, Material mix variance, Material yield variance, Fixed overhead expenditure variance and Fixed overhead volume variance.
Answer:
1. Sales Variances:
Standard Costing – CA Final SCMPE Question Bank 34

2. Material Cost Variance
(i) Computation of Standard Quantity (SQ) of RM
SQ at 96% = \(\frac{69,000 \mathrm{~kg} .}{96 \%}\) = 71,875 kg. .
Standard Costing – CA Final SCMPE Question Bank 35

(iii) Computation of Revised Actual Quantity (RAQ)
Total Actual Qty. = 2,21,000 + 4,79,000 = 7,00,000 kg. RM
Standard Costing – CA Final SCMPE Question Bank 36

3. Variance Computation Chart:
Standard Costing – CA Final SCMPE Question Bank 37

4. Factory Overhead Variances:
Total Factory Overhead Cost Variance = ₹ 5,52,000 – ₹ 5,08,000
= ₹ 44,000
Standard Costing – CA Final SCMPE Question Bank 38

Standard Costing – CA Final SCMPE Question Bank

Question 19.
Trident Toys Ltd. manufactures a single product and the standard cost system is followed. Standard cost per unit is worked out as follows: (May 2018, 12 marks)
Materials (10 Kgs. @ ₹4 Per Kg) = ₹ 40
Labour (8 hours @ ₹ 8 per hour) = ₹ 64
Variable overheads (8 hours @ ₹ 3 per hour) = ₹ 24
Fixed overheads (8 hours @ ₹ 3 per hour) = ₹ 24
Standard Profit = ₹ 56

Overheads are allocated on the basis of direct labour hours. In the month of April 2018, there was no difference between the budgeted and actual selling price and there were no opening or closing stock during the period. The other details for the month of April 2018 are as under:

Budgeted Actual
Production and Sales 2000 Units 1800 Units
Direct Materials 20,000 Kgs. @ ₹ 4 per kg 20,000 Kgs. @ ₹ 4 per kg
Direct Labour 16000 Hrs. @ ₹ 8 per Hr 14800 Hrs. @ ₹ 8 per Hr
Variable Overheads ₹ 48,000 ₹ 44,400
Fixed Overheads ₹ 48,000 ₹ 48,000

Required:
I. Reconcile the budgeted and actual profit with the help of variances according to each of the following method:
(a) The conventional method
(b) The relevant cost method assuming that
(i) Materials are scarce and are restricted to supply of 20000 Kgs. for the period.
(ii) Labour hours are limited and available hours are only 16000 hours for the period.
(iii) There are no scarce inputs.
Answer:
(I) Computation of Variances
Material Usage Variance = Standard Price × (Standard Quantity – Actual Quantity)
= ₹ 4.00 × (18,000* Kgs. – 20,000 Kgs.)
= ₹ 8,000 (A)
* (1800 units × \(\frac{20,000 \mathrm{kgs} .}{2000 \text { units }}\))

Standard Costing – CA Final SCMPE Question Bank

Labour Efficiency Variance = Standard Rate × (Standard Hours – Actual Hours)
= ₹ 8.00 × (14,400* hrs. – 14,800 hrs.)
= ₹ 3,200 (A)
*( 1800 units × \(\frac{16,000 \mathrm{hrs} .}{2000 \text { units }}\))
Variable Overhead Efficiency Variance
= Standard Variable Overheads for Production – Budgeted Variable Overheads for Actual hours
= (14,400 hrs. × ₹ 3.00) – (₹ 3.00 × 14,800 hrs.)
= ₹ 1,200 (A) ‘
Fixed Overhead Volume Variance
= Absorbed Fixed Overheads – Budgeted Fixed Overheads
= (14,400 hrs. × ₹ 3.00) – (16,000 hrs. × ₹ 3.00)
= ₹ 4,800 (A)
Sales Margin Volume Variance = Standard Margin – Budgeted Margin
= (1,800 units × ₹ 56.00) – (2,000 units × ₹ 56.00)
= ₹ 11,200 (A)
Sales Contribution Volume Variance
= Standard Contribution – Budgeted Contribution
= (1,800 units × ₹ 80.00) – (2,000 units × ₹ 80.00)
= 116,000 (A)

Statement Showing “Reconciliation Between Budgeted Profit & Actual Profit”

Particulars Convention al Method (₹) Relevant Cost Method (₹)
Scarce Material Scarce Labour No Scarce Inputs
Budgeted Profit (2,000 units × ₹ 56) 1,12,000 1,12,000 1,12,000 1,12,000
Sales Volume Variance 11.200(A) NIL* 12,000$ (A) 16,000 (A)
Material Usage Variance 8,000 (A) 24,000 (A) 8,000 (A) 8,000 (A)
Labour Efficiency Variance 3,200 (A) 3,200 (A) 7,200 (A) 3,200 (A)
Variable Overhead Efficiency Variance 1,200 (A) 1.200(A) 1,200 (A) 1,200 (A)
Fixed Overhead Volume Variance 4,800 (A) N.A.# N.A. # N.A. #
Actual Profit 83,600 83,600 83,600 83,600

Standard Costing – CA Final SCMPE Question Bank

Notes:
Scarce Material
Based on conventional method, direct material usage variance is ₹ 8,000 (A) i.e. 2,000 Kg. × ₹ 4. In this situation material is scarce, and, therefore, material cost variance based on relevant cost method should also include contribution lost per unit of material. Excess usage of 2,000 Kg. leads to lost contribution of ₹ 16,000 i.e. 2,000 Kgs, × ₹ 8. Total material usage variance based on relevant cost method, when material is scarce will be:

₹ 8,000 (A) + ₹ 16,000 (A) = ₹ 24,000 (A). Since labour is not scarce, labour variances are identical to conventional method.

Excess usage of 2,000 Kgs. leads to loss of contribution from 200 units i.e. ₹ 16,000 (200 units × ₹ 80). It is not the function of the sales manager to use material efficiently. Hence, loss of contribution from 200 units should be excluded while computing sales contribution volume variance.

Therefore, sales contribution volume variance, when materials are scarce will be NIL i,e. ₹ 16,000 (A) – ₹ 16,000 (A).

Scarce Labour
Material is no longer scarce, and, therefore, the direct material variances are same as in conventional method. In conventional method, excess labour hours used are: 14,400 hrs.

– 14,800 hrs. = 400 hrs. Contribution lost per hour = ₹ 10. Therefore, total contribution lost, when labour is scarce will be: 400 hrs. × ₹ 10 = ? 4,000. Therefore, total labour efficiency variance, when labour hours are scarce will be ₹ 7,200 (A) i.e. ₹ 3,200 (A) + ₹ 4,000 (A).

Excess usage of 400 hrs. leads to loss of contribution from 50 units i.e. ₹ 4,000 (50 units × ₹ 80). It is not the function of the sales manager to use labour hours efficiently . Hence, loss of contribution from 50 units should be excluded while computing sales contribution volume Variance. ($)→

Therefore, sales contribution volume variance, when labour hours are Scarce will be ₹ 12,000 (A) i.e. ₹ 16,000 (A) – ₹ 4,000 (A).
Fixed Overhead Volume Variance
(#)→
The fixed overhead volume variance does not arise in marginal costing system. In absorption costing system, it represents the value of the under or over absorbed fixed overheads due to change in production volume. When marginal costing is in use there is no overhead volume variance, because marginal costing does not absorb fixed overheads.

Standard Costing – CA Final SCMPE Question Bank

Question 20.
Apple Ltd., is following three variances method to analyse and understand production overhead variances. The three variances for a particular year were reported as given below: (Nov 2018, 10 marks)
Standard Costing – CA Final SCMPE Question Bank 39

The other particulars furnished from the records of the company are :
Standard machine hours for the year : 11500
Closing balance in the production Overhead
Control Account : ₹ 18,00,000
Fixed overhead rate per hour : ₹ 125
Variable overhead rate per hour : ₹ 80

Required:
Compute the following by considering the additional information also:
(i) Actual machine hours
(ii) Budgeted machine hours
(iii) Total Fixed Production Overhead amount
(iv) Applied Production Overhead amount.

Additional Information:

  • Expenditure variance was computed totally for fixed and variable overheads.
  • Volume variance is applicable to fixed overhead only.
  • Efficiency variance is applicable only to variable overhead and fixed overhead efficiency variance was already included in volume variance.

Answer:
Given Production Overhead Volume Variance = 1,00,000 (F)
Therefore, Fixed Overhead Volume Variance = 1,00,000 (F)
(As per the additional information provided)
1,00,000 (F) = (Budgeted Hours – Standard Hours for Actual Production) × Recovery Rate per hour for Fixed Overheads
1,00,000 (F) = (Budgeted Hours – 11,500 hours) × 125
800 (F) = Budgeted Hours – 11,500 hours
Budgeted Hours = 10,700 hours.
Production Overhead Efficiency Variance = 48,000 (F)
(Standard Hours for Actual Production – Actual Hours) × Recovery Rate per hour for Variable Overheads
48,000 (F) = (11,500 – Actual Hours) ×80
600 (F) = 11,500 – Actual Hours
Since variable overhead efficiency variance is favourable, Actual Hours will be less than standard Hours.
Actual Hours = 11500 – 600
Actual Hours = 10900 hours
Applied Production Overhead (Absorbed)
1 = (Standard Hours for Actual Production x Recovery Rate per hour for fixed and variable overheads)
= 11500 × 205
Applied Production Overhead = ₹ 23,57,500/-
Production Overhead = ₹ 18,00,000 – ₹ 94,000 A + ₹ 1,00,000 F +₹ 48,000 F
= ₹ 18,54,000.

Standard Costing – CA Final SCMPE Question Bank

Alternative Answer:
(i) Calculation of Actual Machine Hours
Efficiency Variance = ₹ 48,000 (F) given
= Standard Variable Overhead Rate per Hour × (Standard Hours – Actual Hours)
₹ 48.000(F) = ₹ 80 × (11,500 hrs. – Actual Hours)
Actual Hours = 10,900 hrs.

(ii) Budgeted Machine Hours
Volume Variance = ₹ 1,00,000 (F)
= Standard Fixed Overhead Rate per Hour × (Standard Hours – Budgeted Hours)
₹ 1,00,000 (F) = ₹ 125 × (11, 500 hrs. – Budgeted Hours)
Budgeted Hours = 10,700 hrs.

(iii) Total Fixed Production Overhead*
Fixed Production Overhead = Standard Fixed Overhead Rate per Hour × Budgeted Hours
= ₹ 125 × 10, 700 hrs.
= ₹ 13,37,500
* Assumed Budgeted

(iv) Applied Manufacturing Overhead
= Standard Overhead Rate per Hour × Standard , Hours
= ₹ 205 × 11, 500 hrs.
= ₹ 23,57,500
Alternative (iii) & (iv)
(iii) Total Fixed Production Overhead
Expenditure Variance = Fixed Production Overhead (Budgeted) + Budgeted Variable Overheads for Actual Hours – Actual Overheads
₹ 94,000 (A) = Fixed Production Overhead + 10,900 hrs. × ₹ 80 – ₹ 18,00,000
Fixed Production Overhead = ₹ 8,34,000

Standard Costing – CA Final SCMPE Question Bank

(iv) Applied Manufacturing Overhead
= Actual Overhead Incurred + Total Variance
= ₹ 18,00,000 + ₹ 54,000
= ₹ 18,54,000

Working Notes:
Total Variance = Expenditure Variance + Efficiency Variance + Volume Variance
= ₹ 94,000 (A) + ₹ 48,000 (F) + ₹ 1,00,000 (F)
= ₹ 54,000 (F)

Standard Costing – CA Final SCMPE Question Bank

Question 21.
GRV is a chemical processing company that produces sprays used by farmers to protect their crops. One of these sprays ‘Agrofresh’ is made by using either chemical A or chemical B. To produce one litre of Agrofresh spray they have the option to use either 12 litres of chemical A or 12 litres of chemical B. During the financial year, the purchase department of GRV has planned to use chemical B as it appeared that it would be the cheaper of the two and their plans were based on a cost of chemical B of ₹ 15 per litre. Due to subsequent market movement during the year the actual prices changed and if the concerned department had purchased efficiently, the cost would have been
Chemical A ₹ 15.40 per litre
Chemical B ₹ 16.00 per litre
Production of Agrofresh spray was 1000 litres and the usage of chemical B was 12800 litres at a cost of ₹ 2,09,920.

You are the CEO of GRV and the Management Accountant has sent to you the following suggestions through e-mail: (May 2019)

“I feel that in our particular circumstances the traditional approach to variance analysis is of little use as for some of our products we can utilize one of several equally suitable chemicals and we always plan to use such chemical which will lead to cheapest production costs.
However due to sharp market movements, we are frequently trapped by the sharp price changes which lead to the choice of expensive alternative at the end.”

To check the reality in the content of the mail, your CEO asked you, the Cost Accountant of the company:
(i) to calculate the material variances for Agrofresh by using (6 marks)

  • Traditional Variance Analysis
  • Planning and Operational Variances

(ii) to analyse how planning and operational variances approached the variances. (2 marks)
(iii) to analyse how the advanced variances are useful to your organisation. (2 marks)
Answer:
(i) Traditional Variances:
Usage Variance = (12,000 litre – 12,800 litre) × ₹ 15
= ₹ 12,000 (A)
Price Variance = (₹ 15 – ₹ 16.4) × 12,800 litre
= 17,920 (A)
Total Variance = ₹ 12,000 (A) + ₹ 17,920 (A)
= ₹ 29,920 (A)

Standard Costing – CA Final SCMPE Question Bank

Operational variances:
Usage Variance = (12,000 litre – 12,800 litre) × ₹ 16
= ₹ 12,800 (A)
Price Variance = (₹ 16 – ₹ 16.40) × 12,800 litre
= ₹ 5,120 (A)
Total Variance = ₹ 12,800 (A)+ ₹ 5,120(A)
= ₹ 17,920 (A)

Planning Variances:
Controllable = (₹ 15.40 – ₹ 16) × 12,000 litre
= ₹ 7200(A)
Uncontrollable Variance = (₹ 15.00 – ₹ 15.40) × 12,000 litre
= ₹ 4,800 (A)
Total Variance = ₹ 7,200 (F) + ₹ 4,800 (A)
= ₹ 12,000 (A)
Reconciliation = 17,920 (A) + ₹ 12,000(A)
= ₹ 29,920 (A)

(ii) A planning variance simply compares a revised standard to the original standard. An operational variance simply compares the actual results against the revised amount. Controllable variance are those variances which arises due to inefficiently of a cost central department. Uncontrollable variances are those variances which arises due to factors beyond the control of the management or concerned department of the organization.

(iii) Planning variances are generally not controllable, where a revision of standards is required due to environmental / technological changes that were not anticipated at the time the budget was prepared, the planning variances are truely uncontrollable. However, standards that failed to anticipate known market trends when they were set will reflect faulty standard – setting : it could be argued that these variances were controllable at the planning stage.

Standard Costing – CA Final SCMPE Question Bank

Question 22.
SPS Limited uses activity based costing to allocate variable manufacturing overhead costs to products. The company identified three activities with the following information for last quarter: (Nov 2019)

Activity Standard Rate Standard Quantity per unit produced Actual Costs Actual Quantity
Indirect Materials ₹ 20 per kilogram 0.5 kilogram per unit ₹? 9,40,000 48,000 kilogram
Product Testing ₹ 3 per test minute 10 minutes per unit ₹ 22,50,000 7,40,000 test minutes
Energy ₹ 0.20 per minute of machine time 4 minutes of machine time per unit ₹ 70,000 3,60,000 minutes of machine time

The company produced 80,000 units in the last quarter. Company policy is to investigate all variances above 5% of the flexible budget amount for each activity.

Required:
(i) Calculate variable overhead expenditure variance and variable overhead efficiency variance for each of the activities using activity based costing. Clearly indicate each variance as favourable or unfavourable/ adverse. (6 marks)
(ii) Interpret the results of variable overhead efficiency variance as calculated in (i) above in respect of indirect materials and product testing activity. (2 marks)
(iii) Identify the variances that should be investigated according to company, policy. Show calculations to support your answer. (2 marks)
Answer:
(i) 1. Indirect Materials:
Variable overhead Expenditure Variance = (Standard Rate – Actual Rate) × Actual Quantity
= (₹ 20 – \(\frac{₹ 9,40,000}{48,000 \mathrm{~kg}}\)) × 48,000 kg
= ₹ 20,000 (F)
Variable overhead Efficiency Variance = (Standard Qty. for Actual – Actual Quantity) × Standard Rate
= (80,000 × 0.5 – 48,000) × ₹ 20
= ₹ 1,60,000 (A)

Standard Costing – CA Final SCMPE Question Bank

2. Product Testing:
Variable overheads Expenditure Variance = (₹ 3 – \(\frac{₹ 22,50,000}{7,40,000}\)) × 7,40,000
= ₹ 30,000 (A)
Variable overhead Efficiency Variance = (80,000 × 10 – 7,40,000) × ₹ 3
= ₹ 1,80,000 (F)

3. Energy:
Variable overheads Expenditure Variance = (₹ 0.2 0 – \(\frac{₹ 70,000}{3,60,000}\)) × 3,60,000
= ₹ 2,000 (F)
Variable overheads Efficiency = (80,000 × 4 – 3,60,000) × ₹ 0.20
= ₹ 8,000 (A)

(ii) In case of Indirect material, the variable overhead efficiency variance is ₹ 1,60,000 (A). Which indicates that actual production quantity have been produced in more time as allowed In case of product testing, variable overhead efficiency variance is ₹ 1,80,000 (F). Which indicates that the actual production have been made in less time as allowed.

(iii) 1. Indirect Material:
= (80,000 units × 0.5 kg. per unit × ₹ 20)
= ₹ 8,00,000
Investigation to be done if, indirect material net variance is more than ₹ 40,000 (i.e. ₹ 8,00,000 × 5%) ,
Net Variable overhead cost variance = ₹ 1,60,000 (A) – ₹ 20,000 (F)
= ₹ 1,40,000 (A)
So, Indirect Material activity variances as shall be investigated.

2. Product Testing:
= (80,000 units × 10 min per unit) × ₹ 3 per test minute = ₹ 24,00,000
Investigation to be done if, product Testing net variable is more than ₹ 1,20,000 (i.e. ₹ 24,00,000 × 5%)
Net Variable Cost Variance = ₹ 180.000(F) – ₹ 30,000 (A)
= ₹ 1,50,000 (F)
So, product testing should be investigated

Standard Costing – CA Final SCMPE Question Bank

3. Energy:
(80,000 units × 4 min × ₹ 0.20) = ₹ 64,000
Investigation to be done if, product testing net variable is more than ₹ 3,200 i.e. ₹ 64,000 × 5%).
Net Variable Cost Variance = ₹ 8,000 (A) – ₹ 2,000 (F) = ₹ 6,000 (A) .
So, energy activity variance should be investigated.

Alternate Answer:
(i) Indirect Materials
Efficiency Variance = Cost Impact of undertaking activities more/ less than standard
= (0.50 kg. × 80,000units – 48,000 kg.) × ₹ 20
= ₹ 1,60,000 (A)
Expenditure Variance = Cost impact of paying more/ less than standard for actual activities undertaken
= 48,000kg. × ₹ 20 – ₹ 9,40,000
= ₹ 20,000 (F)

Product Testing
Efficiency Variance = Cost Impact of undertaking activities more/ less than standard
= (10 mins. × 80,000 units – 7,40,000 mins.) × ₹ 3
= ₹1,80,000 (F)
Expenditure Variance = Cost impact of paying more/ less than standard for actual activities undertaken
= 7,40,000mins × ₹ 3 – ₹ 22,50,000
= ₹ 30,000 (A)

Energy
Efficiency Variance = Cost Impact of undertaking activities more/ less than standard
= (4 mins, × 80,000 units – 3,60,000 mins.) × ₹ 0.20
= ₹ 8,000 (A)
Expenditure Variance = Cost impact of paying more/ less than standard for actual activities undertaken
= 3,60,000mins × ₹ 0.20 – ₹ 70,000
= ₹ 2,000 (F)

Standard Costing – CA Final SCMPE Question Bank

(ii) Indirect Materials
SPS actually spent 48,000 kg. or 8,000 kg. more than the standard allows. At a predetermined rate of ₹ 20 per kg., efficiency variance is 1,60,000 (A). Since actual quantity were higher than the standard, the variance is unfavorable. This adverse variance, could have been caused by the inferior quality, result of carelessness handling of materials by production workers or could as a result of change in methods of production, product specifications or the way in which quality of the product is checked or controlled.

Product Testing
Favorable efficiency variance amounting to ₹ 1,80,000 indicates that fewer testing minutes were expended during the quarter than the standard minutes required for the level of actual output. This may be due to employment of a higher skilled labor or improvement of skills of existing workforce through training and development leading to improved productivity etc.

(iii) Flexible Budget

Indirect Materials = (0.50 kg. × 80,000 units) × ₹ 20
= ₹ 8,00,000
= ₹ 8,00,000 × 5%
= ₹ 40,000
Product Testing = (10 mins. × 80,000 units) × ₹ 3
= ₹ 24,00,000
= ₹ 24,00,000 × 5%
= ₹ 1,20,000
Energy = (4 mins. × 80,000)  × ₹ 0.20
= ₹ 64,000
= ₹ 64,000 × 5%
= ₹ 3,200

Efficiency Variance for all the three activities are more than 5% of their flexible budget amount. So, according to the company policy, efficiency variances should be investigated.

Standard Costing – CA Final SCMPE Question Bank

Question 23.
KRI Sanitation Ltd. manufactures a single product and the standard cost system is followed. Standard cost per unit is calculated as below: (Nov 2020)

Particulars Amount (₹)
Direct Materials (4 kg. @ ₹ 7 kg.) 28
Direct Labour (5 Hours @ ₹ 9 per hour) 45
Variable overheads (6 Hours @ ₹ 2 per hour) 12

The other data for the month of June 2020 is given below:

Particulars Budgeted Actual
Production and Sales 15,000 units 13,800 units
Direct Material 60,000 kg @ ₹ 7 per kg. 60,000 kg. @ ₹ 7 per kg.
Direct Labour 75,000 Hours @ ₹ 9 per hour ₹ 5,69,600 (for 71,200 hours)
Variable Overheads 1,80,000 1,72,500

Required
(i) Calculate following variances:

  • Direct Labour Rate Variance
  • Direct Labour Efficiency Variance (3 marks)

(ii) Interpret the result. (7 marks)

Standard Costing – CA Final SCMPE Question Bank

Question 24.
Sri Manufacturers Ltd. manufactures a single product. Standard cost per unit is as follows: (Jan 2021)

Particulars
Materials 12 kgs × ₹ 5 per kg 60
Labour 10 hrs × ₹ 7 per hour 70
Variable Overheads 10 hrs × ₹ 3 per hour 30
Fixed Overheads 10 hrs × ₹ 3 per hour 30
Profit 60
Selling Price 250

Overheads are allocated on the basis of direct labour hours. In the month of March 2020 there was no difference between the budgeted and actual selling price and there was no opening and closing stock during the period. The other details for the month of March 2020 are as under:

Budgeted Actual
Product and sales

Direct Materials

Direct Labour

Variable Overheads

Fixed Overheads

2500 units

30,000  kgs @ 5 per kg

25,000 hrs @ ₹ 7 per hour

₹ 75,000

₹ 75,000

2000 units

30,000 kgs @ 5 per kg

22,500 hrs @ ₹ 7 per hour

₹ 67,500

₹ 75,000

Standard Costing – CA Final SCMPE Question Bank

Required:
Reconcile the budgeted and actual profit with the help of variances according to each of the following methods:
(i) The conventional method (3 marks)
(ii) The relevant cost method assuming that
(a) Materials are scarce and are restricted to supply of 30,000 kgs for the period. (3 marks)
(b) Labour hours are limited and available hours are only 25,000 hour for the period. (4 marks)

Leave a Comment

Your email address will not be published. Required fields are marked *